Kilburn regeneration: Ballymore appointed as vacant estate blocks remain exposed
Brent Council has named Ballymore as sole developer for the remaining phase of South Kilburn’s regeneration, while vacant blocks at Hereford House and Exeter Court have faced fly-tipping and trespassing.

In Kilburn, Brent Council has appointed Ballymore as sole developer for the remaining phase of the South Kilburn regeneration programme, offering a route forward for a scheme delayed by financial pressures and problems with earlier developments. The appointment is subject to a call-in period.
Council papers say previous developers faced viability challenges and difficult economic conditions. They also record complaints about poor build quality in completed phases, alongside noise, dust, traffic and increased anti-social behaviour near delayed sites. The programme aims to replace 1960s housing with about 2,400 homes, including more than 1,400 for existing South Kilburn residents.
What is planned for the vacant blocks?
Hereford House and Exeter Court are vacant, fenced-off blocks where construction has yet to begin. Council plans schedule work to start in 2026 and completion for summer 2029. The proposal is for 250 homes, including 109 social-rent affordable homes, as well as a new park and retail space.
The site has faced fly-tipping, squatters and anti-social behaviour since residents moved out in 2021. Some fence panels remained broken, reportedly making it easier for trespassers to get in. The council has not announced an updated construction timetable or provided a new completion date.
How much of the programme remains?
Council documents say 1,954 homes have been delivered or are under construction so far, including 1,239 social-rent homes. The council’s initial target was to finish the entire programme by summer 2029, although some developments have not started. The papers do not set out a revised overall completion date.
Other work is under way across the estate. Construction on the 225-home NWCC scheme began in spring 2024 and is due to finish in summer 2029, while phase four of the North West Quarter is targeted for completion by the end of 2026. Ballymore is also set to deliver 18 council homes at the Carlton and Granville centres, where the wider project is due to finish in late 2026.